The Ideas Genie Community Forum

Ideas Genie Pro => General discussion => Topic started by: roiphil on March 30, 2015, 03:14:33 PM

Title: Rescheduling tasks
Post by: roiphil on March 30, 2015, 03:14:33 PM
George, as you know i am figuring out how to use IG PRO for my christmas trees production, quick question in Tasks it is possible to assign a task a month and reschedule if you like for the next year, is it possible though to reschedule for more than 1 following year, Thanks phil
Title: Re: Rescheduling tasks
Post by: ideasguy on March 30, 2015, 07:17:49 PM
If no Status info was added (i.e. done dates not recorded) then its a simple matter of editing and changing the task Phil.

By design, Ideas Genie expects a new task to be manually created for next year if a task is repetitive.

However, I will look at allowing a task to be duplicated in Ideas Genie Pro 6.
Would that help?
Title: Re: Rescheduling tasks
Post by: roiphil on March 31, 2015, 09:33:14 AM
George that would be great, thanks, certain tasks i do every year, same month, feeding, weedkilling etc, it a way to remind myself when to order feed, from where and when to do